An expansion of an existing brownfields plant, upsizing the capability and capacity of the Ayr Water Treatment Plant to 14 megalitres a day.
The Ayr Water Treatment Plant is an expansion of an existing brownfields plant, upsizing the capability and capacity of the existing treatment plant to 14ML per day. The scope of the project included the construction of a fully integrated facility, covering civil, structural, mechanical, electrical and controls.
A 34m x 7m block building houses tanks, analysers, dosing systems for caustic soda, potassium permanganate, alum and polymer, and switchboards, integrated with the existing chlorine dosing system.
Supporting infrastructure included an HV switchroom building, an air scour building, a sludge pump station discharging waste sludge to the town sewer, and a fibreglass packaged supernatant pump station returning water to the head of the plant.
SCADA programming and controls integration covered compilation of a detailed functional description, programming workshops, offsite programming and SCADA integration to suit the existing system.
Pre-commissioning, testing and commissioning covered testing of all pipes, structures and equipment, progressive energisation of six switchboards and field boards, pre-commissioning of all equipment, wet commissioning, process commissioning, a proving period and handover.
We deliver water and wastewater treatment upgrades for councils and water authorities across Queensland and New South Wales.